Fidson Nigeria Turnkey Pharmaceutical Project
Fidson Healthcare's multi-million dollar plant in Nigeria had stopped. Fabtech took over the project and commissioned the scope of its contract in 15 months.
We reply within 24 hours.
- A dosage line is a production line for one type of medicine.
- HVAC means heating, ventilation and air conditioning.
- Commissioning means starting each system and checking that it runs.
- "To scope" means that every item in the contract was commissioned.
On this page
What Fidson set out to build
Fidson Healthcare in Nigeria planned six dosage lines in one plant. Fabtech's contract covered the cleanrooms, HVAC, utilities, high purity water and laboratory.
More detail
The plan was an ultra-modern facility at Sango Otta, Ogun State Nigeria. It would have high-tech machinery and be GMP and WHO compliant, in line with global standards.
The plant would meet the needs of Nigerian and West African markets.
It would also make Fidson's position as a leader in the Nigerian pharma industry stronger, and make the company known around the world.
The client is Fidson Healthcare Plc. Fidson calls this site its flagship.
Six dosage lines in one plant makes this project unusual. Each line uses a different process and different machines.
Each one also needs a different level of cleanliness. The contract below shows the rooms, the air, the water and the utilities that Fabtech delivered for the plant.
Where the project stood when we were called
Work on Fidson's flagship state-of-the-art $40 million plant had stopped completely. Fidson's contractor was working in unfamiliar territory.
More detail
It could not bring in the right resources, so the project stalled for over 18 months.
What was in our contract
Our $6.5 million contract included the design, engineering, supply, installation, validation and commissioning of:
More detail
Validation is the testing that proves each system works as it should.
This is a full turnkey pharmaceutical project scope. One contract covers the rooms, the air, the water, the utilities and the services.
The scope is handed over commissioned. Fabtech designs and supplies the purified water systems and the cleanroom and clean-air scope as part of the same contract.
What we did
It looked as if the plant would never be finished. Then Fabtech was invited to take over the project.
More detail
We sent in our projects planning, execution and management team. We commissioned the entire project to scope in 15 months.
Taking over a stalled project is a different job from starting a new one. Part of the site is already built, and there is no spare time left in the schedule.
A greenfield project starts on empty land. A brownfield project works with buildings that already exist.
So this takeover was a brownfield problem on what began as a greenfield site.
What was in our contract
- Modular cleanroom infrastructure, 150 units of HVAC, cooling and dehumidifying systems
- Piping and connection of all utilities for steam, air, compressed natural gas, diesel etc
- Mechanical, electrical and plumbing systems
- High purity water treatment plant
- Fire prevention and safety equipment
- A best-in-class laboratory and R&D centre
Where the facility is now
The factory is now the largest pharma facility in Nigeria and West Africa. It has been up and running for 19 months without malfunctions.
Several visitors have said that it meets world-class standards. They came from global regulatory bodies and from private and public enterprise.
The facility makes pharmaceutical products at large scale. They are made to meet the healthcare needs of people in Nigeria and in West African markets.
Together, Fidson and Fabtech are saving lives. They do this by making affordable medicines available to the people who need them.

Key fact Detail
- Time to commission Fabtech's scope
- 15 months
- Time the project had been stalled
- Over 18 months
- Value of Fabtech's contract
- $6.5 million
- What Fabtech's contract covered
- Cleanrooms, HVAC, utilities, high purity water and laboratory
- Client
- Fidson Healthcare Plc
- Place
- Sango Otta, Ogun State, Nigeria
What Fidson said
“Fabtech's competence was clear from the very day they were awarded the contract. They brought unassailable professionalism, versatility, responsiveness, and speed to bear on our project despite various changes introduced in the course of execution. They delivered well within the timeline promised without any major injuries to any worker. Fabtech is indeed a reliable partner, focused on quality, timely delivery and value for money start-to-finish projects. I gladly recommend them to anyone requiring their services, anywhere in the world.”
FAQ
Who built the Fidson Healthcare plant in Nigeria?
Fabtech built what its contract covered. The project had been stalled for more than 18 months when we took it over. We commissioned the scope of our contract in 15 months. Our $6.5 million contract covered cleanroom infrastructure, HVAC, utilities, high purity water, MEP (mechanical, electrical and plumbing), fire safety, and the laboratory and R&D centre.
Where is the Fidson plant?
The plant is in Sango Otta, Ogun State, Nigeria. It serves the Nigerian and West African markets.
What does the facility make?
Fidson Healthcare in Nigeria planned six dosage lines in one plant. Fabtech's contract covered the cleanrooms, HVAC, utilities, high purity water and laboratory. The facility makes pharmaceutical products at large scale for Nigeria and West African markets.
Can you take over a project another contractor has stopped?
Yes. The Fidson project had stalled for over 18 months, and Fabtech commissioned the whole scope of its contract in 15 months.
How long did it take?
Fifteen months, from taking over to commissioning the entire scope. Before that, the plant had been stopped for over eighteen months.